Olkaria V geothermal power station in Hell's Gate National Park, Kenya, not the Olkaria I plant in this story (file photo, 2019).
Olkaria V geothermal power station in Hell's Gate National Park, Kenya, not the Olkaria I plant in this story (file photo, 2019). Photo: Macabe5387 / Wikimedia Commons, CC BY-SA 4.0

There is a later report on this (26 Nov 2026 18:33): Kenya's KenGen targets 250 MW of new renewable power by 2027 · all 2 reports

Kenya Electricity Generating Company (KenGen) has completed a three-year rehabilitation of Olkaria I, Kenya's oldest geothermal power station, managing director Peter Njenga said at a press briefing in Naivasha. KenGen's project page puts the plant's installed capacity at 63.3 megawatts (MW), up from 45 MW.

"We are happy to announce that the rehabilitation works of Olkaria I are now complete," Njenga said, as quoted by Citizen Digital on 25 November. He said trials were under way and that President William Ruto is scheduled to commission the plant on 7 December. The station generated about 45 MW before the works.

ThinkGeoEnergy, a geothermal industry news site, reported on 30 October that KenGen announced the completion at its annual general meeting.

The engineering, procurement and construction (EPC) contractor is SEPCOIII Electric Power Construction Company Limited, a subsidiary of Power Construction Corporation of China (POWERCHINA), according to ThinkGeoEnergy. The Star and Business Daily reported the award in March 2024, together with a contract for Japan's Toshiba Energy Systems and Solutions Corporation (Toshiba ESS) to supply steam turbines and generators for the plant's three units. Completion was then scheduled for December 2026. KenGen did not disclose the value of either contract, Business Daily reported.

SEPCOIII had won more than 70 overseas power and desalination projects under EPC contracts in 28 countries, including Saudi Arabia, the UAE, Morocco, Uzbekistan and Bangladesh, China Energy News, a People's Daily group paper, reported in October 2023. It listed a Kenyan geothermal project among the company's green energy work.

The plant was closed in May 2023 to make way for the works. KenGen said in 2024 that the upgrade would raise electricity output by up to 40 per cent compared with existing conventional models, and Njenga said then that the company was "confident the project will be completed on time and within budget".

Unit 3 came online in May 2026 and Unit 2 followed by July 2026, when a KenGen financial report put the rehabilitation at 92 per cent complete.

The works fitted new generators and turbines on Units 1, 2 and 3, redesigned the steam-field pipeline layout and optimised separators, control valves, cooling systems and exhaust stations. New condensers, circulating water pumps and cooling towers replaced ageing equipment. Steam Srl was the owner's engineer.

KenGen's project page, which describes Olkaria I in Nakuru County as the first geothermal power plant in Africa, also lists the rehabilitation of the steam-gathering system and the construction of a gas-insulated substation, and says the upgrade will extend the plant's operating life by more than 25 years.

The rehabilitation is part of a KSh 15.5 billion (about US$119.3 million) KenGen power infrastructure investment for 2025 and 2026, according to ThinkGeoEnergy. The same portfolio included a battery storage project and the redevelopment of a hydropower station.

Kenya's power demand has risen sharply against limited production, Citizen Digital reported. Njenga said five investors were already on the ground at the Olkaria green energy park, and that a fertiliser producer already there would need 165 MW from geothermal. KenGen plans to use an upcoming three-day sustainable energy conference in the Olkaria area to meet financiers.

Drafted and translated with AI assistance; reviewed and published by editor . How we use AI

Sources

Reporting Desk research, human-reviewed Sources 6 Published 25 Nov 2026 Corrections none How we check

  1. Olkaria I: Kenya's oldest geothermal station steams back to life citizen.digital about
  2. KenGen increases capacity of Olkaria I geothermal power station following rehabilitation thinkgeoenergy.com
  3. KenGen awards multibillion contract to modernise Olkaria I power plant the-star.co.ke about
  4. Chinese firm wins KenGen's geothermal plant upgrade job businessdailyafrica.com about
  5. Olkaria 1 Rehabilitation Project (KenGen project page) kengen.co.ke
  6. 访中国电建集团山东电力建设第三工程有限公司党委书记、董事长、总经理赵启明(《中国能源报》) paper.people.com.cn

Got a tip? Tell us →

Sign in to comment →