Kenyan MPs back NSSF stake in toll road built with China Road and Bridge

A container truck and a car on a busy Kenyan highway (file photo, 2013).
A container truck and a car on a busy Kenyan highway (file photo, 2013). Photo: Fica Vision / Du Fengyan

There is a later report on this (18 Nov 2026 18:43): Kenya's Mbadi says China Road and Bridge is an investor in Rironi–Mau Summit toll road · all 2 reports

Parliament's Departmental Committee on Social Protection has endorsed the National Social Security Fund's (NSSF) stake in the Rironi–Mau Summit toll road, a 233-km dualling project in which NSSF and China Road and Bridge Corporation are building two of the three sections, the official Kenya News Agency (KNA) reported on 16 November. Works are about 40% complete.

Committee chairperson Alice Ng'ang'a said the Fund "made the right decision", as quoted by KNA. MPs toured the 81-km Rironi–Gilgil section with the NSSF board, led by chairman David Kariuki Njeru, and the Fund's Managing Trustee and chief executive, David Koross.

The road will charge KSh 8 per kilometre, about KSh 648 for the full 81 km between Rironi and Gilgil, across three toll stations. Local traffic that leaves the road before the next toll station pays nothing. Tolls are set by the government through the Kenya National Highways Authority (KeNHA).

The project is a public-private partnership launched in November 2025. Its three sections are Rironi–Naivasha–Gilgil (81 km), Rironi–Mai Mahiu–Naivasha (58 km) and Gilgil–Nakuru–Mau Summit (94 km).

NSSF and China Road and Bridge Corporation are building the first two sections. Shandong Hi-Speed Road and Bridge International Engineering is building the third.

The Rironi–Naivasha section is targeted to open in December 2026 and the full corridor in June 2027. Roads Cabinet Secretary Davis Chirchir has also said the Rironi–Naivasha section will open to traffic in December, the Kenyan news site Kenyans.co.ke reported on 16 November.

The project is financed 25% by equity and 75% by debt. NSSF provides 40% of the equity, and its exposure is limited to that share. Over the 30-year concession, NSSF receives 40% of toll collections and China Road and Bridge Corporation 60%.

NSSF says the investment diversifies its portfolio beyond government bonds and offers steady returns that may help protect pensioners' savings against inflation. Koross cited government assurances that the legal framework will not change, and an agreed minimum toll rate. He described the committee's inspection as part of its oversight of the Fund, meant to confirm that members' money is invested prudently.

Separately, a Gazette notice dated 13 November from the National Land Commission (NLC) lists more parcels for compulsory acquisition for the road, Kenyans.co.ke reported. The parcels are in Nakuru, Kiambu and Nyandarua counties.

The NLC said it intends to delete, correct and add parcels on behalf of KeNHA, under section 110 of the Land Act No. 6 of 2012. Deletions cover parcels of individuals and companies in Limuru, Lari, South Kinangop, Longonot and Naivasha. Corrections cover parcels in Limuru, Lari, South Kinangop and Naivasha.

The new acquisitions include land occupied by the Kenya Wildlife Service and the Naivasha GK Prison, along with individually owned parcels. Land occupied by the Kenya Forest Service at Kinale Forest (12.7921 hectares) is also listed.

Public inquiries on the propriety of the acquisition, compensation and other issues begin on 1 December at 10:00 a.m. at chiefs' offices in the affected areas.

Individuals claiming compensation must submit a written claim with a copy of their national ID, a KRA PIN certificate, land ownership documents and bank account details. Companies must provide certificates of incorporation, CR12 documents, the company's KRA PIN certificate, and ID and KRA PIN documents for each director.

Claims go to the NLC at Ardhi House, 3rd Floor, Room 305, 1st Ngong Avenue, Nairobi, or to the NLC county coordinators' offices in Kiambu, Nakuru and Nyandarua.

Drafted and translated with AI assistance; reviewed and published by editor . How we use AI

Sources

Reporting Desk research, human-reviewed Sources 2 Published 16 Nov 2026 Corrections none How we check

  1. Parliament endorses NSSF's investment in Rironi-Mau Summit Road Project kenyanews.go.ke about
  2. Landowners in 3 Counties Put on Notice Over New Rironi-Mau Summit Acquisitions kenyans.co.ke about