Kenya to open parts of China Road and Bridge Corporation's Naivasha road before Christmas
Kenya's roads ministry said on 21 November that finished sections of the 60 km Rironi–Naivasha road, originally due on 30 October, will open before Christmas.

Kenya's roads ministry said on 21 November that finished sections of the 60 km Rironi–Naivasha road, originally due on 30 October, will open before Christmas.

Kenya's foreign ministry said on 20 November it had flagged off eight ICT students for Huawei training in China, up from five sent in 2025.

Kenya owed China, its largest bilateral lender, KSh601.37 billion at end-September, down KSh3.42 billion, a Treasury bulletin posted on 20 November shows.
Gulf Energy began drilling at Amosing 1 in Turkana on 20 November, with first oil set for 1 December and more than 20,000 barrels a day planned.

China's envoy Guo Haiyan offered on 19 November to help Kisumu County use the zero-tariff access Kenyan goods have had in China since 1 May 2026.

Presidents Museveni and Samia Suluhu Hassan on 19 November opened the Chinese-invested Mpigi plant, which can assemble 4,000 Sinotruk trucks a year.

Treasury CS John Mbadi said on 17 November that China Road and Bridge is a shareholder with NSSF in the Rironi–Mau Summit road, not only its builder, and that tolls will be a bit higher because of the risk.

Parliament's Social Protection committee backed NSSF's investment in the 233-km Rironi–Mau Summit toll road, KNA reported on 16 November.

Nairobi firm Roam Electric buys about 60% of its parts by value from China and assembles 500 e-motorcycles a month, Xinhua reported on 14 November 2026.
Kenya's Thwake Dam is 94.2% complete and impoundment is set for April 2027, Water PS Julius Korir said on 10 November, The Star reported.

KRA chief Adan Mohamed said on 13 November that Chinese records showed about US$10 billion of exports to Kenya while Kenyan Customs captured about US$5 billion, and tied the gap to the export-declaration rule for importers, Kenyans.co.ke reported.

Members of Kenya's National Assembly transport committee asked China Road and Bridge Corporation on 10 November to show evidence that it is engaging Kenyan firms on the KSh 154 billion upgrade of Jomo Kenyatta International Airport in Nairobi, due for completion in mid-2029, The Star and Kenyans.co.ke reported on 11 November.